Purchase orders that Department of Wildlife has placed with NATURAL CHANNEL DESIGN ENGINEERING for FY2027. Click a PO to see line items and detail.
Data as of: October 31, 2026Updated: November 17, 20264 records
- # of Purchase Orders
- 4
- Total Amount
- $131,828.26
- Balance
- $106,423.04
Purchase Orders
4 POs with NATURAL CHANNEL DESIGN ENGINEERING at Department of Wildlife. Click a PO ID to see its line items.
FY2027 · Executive
Filters
| PO ID | Description | Contract ID | PO Date | Total Amount | Amount Expended | Balance |
|---|---|---|---|---|---|---|
| — | — | — | — | $131,828.26 | $25,405.22 | $106,423.04 |
| 0000100780 | Site Visit/Survey, 1 @ $20,543.20Estimated NM GRT 5.25% = $946.26 | 23 516 0000 00024 | 07-21-2026 | $51,796.24 | $21,489.46 | $30,306.78 |
| 0000101535 | Site Visit/Survey:GIS Specialist, Qty-2 hrs @ $126.00Engineering Technician/Ecologist, Qty-40 hrs @ $107.00Survey Equipment, Qty-8 hrs @ $48.00Mileage (1trip, miles), Qty-350 @ $0.70Per Diem (/person./day), QTY-2 @ $160.00 | 23 516 0000 00024 | 10-07-2026 | $37,019.73 | $0.00 | $37,019.73 |
| 0000101019 | Site Assessment, and Reference Reach Survey. Mimbres River Bank Stabilization Maintenance Design Project. River Ranch Wildlife Management Area. 100% Completion Engineering Assessment and Design Services | 23 516 0000 00024 | 08-12-2026 | $27,871.26 | $3,915.76 | $23,955.50 |
| 0000100976 | Pre-Bid Assistance, Qty-2 hours @ $175.00 | 23 516 0000 00024 | 08-07-2026 | $15,141.03 | $0.00 | $15,141.03 |
Showing 1 to 4 of 4 entries